top of page
Long%20Island%20Coastline_edited_edited_edited.jpg

CONSTRUCTION AREAS

AWTF.PNG

Contract 1 AWTF- Advanced Wastewater Treatment Facility (AWTF)

AWTF Contract 1 began in January 2022. The contractor for the contract is Posillico-Bove. The contractor is constructing the new site buildings and has substantially completed the subsurface recharge area work for the new treatment facility infrastructure. 

Below is a picture of how AWTF will look once it's built. 

Picture1.jpg

Contract 2 LPS North - Installation of Low Pressure Sewers (LPS) in the Streets

Contract 2 - Low Pressure Sewers North began in January 2022 and the Contractor is Posillico-Bove. The Contractor will perform the following work activities in this order:

  • Stakeout existing utilities (water, gas, electric, etc) within the project areas using various forms of field markers, including but not limited to wooden stakes, PK nails, ribbon, flags, and paint. 

  • Once the utilities are marked, test pits will be excavated in the street to verify the locations of existing utilities.

  • Excavation of the street and installation of the new sewer main.

  • Excavation to install the new sewer lateral from the new sewer main to the property line of each residence.

  • Restoration of the disturbed areas.

  • Repaving of the streets.

 

The map on the right provides anticipated staging of the work. Residents will be provided with 72-hour minimum advance notice with door hangers when work is to be initiated in their area. An example of the door hanger in English and Spanish is provided below.

Contract 2 LPS

Contract 3 LPS East - Installation of Low Pressure Sewers (LPS) in the Streets

Contract 3 - Low Pressure Sewers East began in January 2022 and the Contractor is Peter Scalamandre & Sons. The Contractor will perform the following work activities in this order:

  • Stakeout existing utilities (water, gas, electric, etc) within the project areas using various forms of field markers, including but not limited to wooden stakes, PK nails, ribbon, flags, and paint. 

  • Once the utilities are marked, test pits will be excavated in the street to verify the locations of existing utilities.

  • Excavation of the street and installation of the new sewer main.

  • Excavation to install the new sewer lateral from the new sewer main to the property line of each residence.

  • Restoration of the disturbed areas.

  • Repaving of the streets.

 

The map on the right provides anticipated staging of the work. Residents will be provided with 72-hour minimum advance notice with door hangers when work is to be initiated in their area. An example of the door hanger in English and Spanish is provided below.

Contract 4 LPS South - Installation of Low Pressure Sewers (LPS) in the Streets

Contract 4  - Low Pressure Sewers North began in December 2022 and the Contractor is Posillico-Bove. The Contractor will perform the following work activities in this order:

  • Stakeout existing utilities (water, gas, electric, etc) within the project areas using various forms of field markers, including but not limited to wooden stakes, PK nails, ribbon, flags, and paint. 

  • Once the utilities are marked, test pits will be excavated in the street to verify the locations of existing utilities.

  • Excavation of the street and installation of the new sewer main.

  • Excavation to install the new sewer lateral from the new sewer main to the property line of each residence.

  • Restoration of the disturbed areas.

  • Repaving of the streets.

 

The map on the right provides anticipated staging of the work. Residents will be provided with 72-hour minimum advance notice with door hangers when work is to be initiated in their area. An example of the door hanger in English and Spanish is provided below.

Back to Top

BACK TO TOP

bottom of page